[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905372":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},905372,585,2,"多选题","木材加工厂规模应根据下列哪些确定？（ ）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","木材来源及其运输方式",true,{"key":16,"text":17,"correct":14},"B","锯材、构件、木模板的需要量和供应计划",{"key":19,"text":20,"correct":14},"C","场内运输条件",{"key":22,"text":23,"correct":24},"D","高峰月的日平均需要量",false,{"key":26,"text":27,"correct":24},"E","原材料的供应运输方式","ABC","木材加工厂主要任务是为工程混凝土浇筑提供钢模不能代替、特殊部位的标准和异型模板，临建工程木制品加工等。木材加工厂规模宜根据工程所需原木总量，木材来源及其运输方式，锯材、构件、木模板的需要量和供应计划，场内运输条件等确定。工作内容主要为锯、刨、开榫等，主要设置卸料场、原料堆场、锯材堆场、机木堆场、模板细木堆场、锯材车间、配料机木车间和模板细木车间等。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（水利）","建筑工程",0]