[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905371":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},905371,585,2,"多选题","S形曲线能直观反映工程项目的（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","实际进展速度",true,{"key":16,"text":17,"correct":18},"B","关键线路",false,{"key":20,"text":21,"correct":14},"C","工程量完成情况",{"key":23,"text":24,"correct":14},"D","后续进度的预测",{"key":26,"text":27,"correct":14},"E","进度超前或拖延时间","ACDE","项目进度控制工程师事先绘制进度计划的S形曲线。在项目施工过程中，每隔一定时间按项目实际进度情况绘制完工进度的S形曲线，并与原计划的S形曲线进行比较，S形曲线可直观反映：①项目的实际进展速度。如果项目实际进展的累计完成量在原计划的S形曲线左侧，表示此时的实际进度比计划进度超前，反之，如果项目实际进展的累计完成量在原计划的S形曲线右侧，表示实际进度比计划进度拖后。②进度超前或拖延时间。③工程量完成情况。④项目后续进度的预测。在S形曲线比较图中，虚线表示项目后续进度若仍按原计划速度实施。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（水利）","建筑工程",0]