[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905368":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},905368,585,2,"多选题","关于质量检查工程量，下列说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","质量检查工程量包括基础处理工程检查工程量",true,{"key":16,"text":17,"correct":18},"B","采用概算定额编制概（估）算时，应计列检查孔的工程量",false,{"key":20,"text":21,"correct":14},"C","采用概算定额时不应计列试验坑的工程量",{"key":23,"text":24,"correct":18},"D","采用预算定额时应计列试验坑的工程量",{"key":26,"text":27,"correct":14},"E","采用预算定额时，选用相应定额计算检查孔的费用","ACE","A项，质量检查工程量包括基础处理工程检查工程量和其他检查工程量。B项，现行概算定额中钻孔灌浆定额已按施工规范要求计入了一定数量的检查孔钻孔、灌浆工程量，故采用概算定额编制概（估）算时，不应计列检查孔的工程量。CD两项，土石方填筑检查所需的挖掘试坑，现行概、预算定额已计入了一定数量的土石坝填筑质量检测所需的试验坑，故采用概、预算定额时不应计列试验坑的工程量。E项，现行预算定额中钻孔灌浆定额不包含检查孔钻孔、灌浆工程量，采用预算定额时，应按灌浆方法和灌浆后的Lu值，选用相应定额计算检查孔的费用。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（水利）","建筑工程",0]