[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905332":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},905332,585,2,"多选题","关于土方超挖量及附加量的原因，下列说法正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","因钻孔的操作中常产生某些偏斜及误差等原因导致石方开挖工程发生超挖",true,{"key":16,"text":17,"correct":14},"B","满足施工需要，必须额外增加的工作量称为附加量",{"key":19,"text":20,"correct":21},"C","附加量是为了满足施工需要，不应限制范围",false,{"key":23,"text":24,"correct":21},"D","石方明挖工程的平面高程一般应不大于0.5m",{"key":26,"text":27,"correct":14},"E","地下工程石方开挖因地质原因产生的超挖根据实际情况确定","ABE","根据规范规定，超挖量和施工附加量的最大允许误差应符合下列规定： ①石方明挖工程的平面高程一般应不大于0.2m。 ②地下工程石方开挖因地质原因产生的超挖根据实际情况确定。 CD选项错。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（水利）","建筑工程",0]