[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905324":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},905324,585,2,"多选题","编制施工总进度时，工程施工总工期应为（ ）之和。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程筹建期",false,{"key":16,"text":17,"correct":18},"B","工程准备期",true,{"key":20,"text":21,"correct":18},"C","主体工程施工期",{"key":23,"text":24,"correct":18},"D","工程完建期",{"key":26,"text":27,"correct":14},"E","工程验收期","BCD","工程建设全过程可划分为工程筹建期、工程准备期、主体工程施工期和工程完建期四个施工时段。编制施工总进度时，工程施工总工期应为后三项工期之和。工程建设相邻两个阶段的工作可交叉进行。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（水利）","建筑工程",0]