[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905321":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},905321,585,2,"多选题","关于施工进度计划的调整，下列说法错误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","活动的进度偏差未超过该活动的自由时差，仍需调整原进度计划",true,{"key":16,"text":17,"correct":18},"B","活动的进度偏差不大于该活动的总时差，则此进度偏差不影响工期",false,{"key":20,"text":21,"correct":18},"C","改变某些活动间的逻辑关系，可以调整施工进度计划",{"key":23,"text":24,"correct":18},"D","可以直接在网络图上缩短某些活动的持续时间",{"key":26,"text":27,"correct":14},"E","进度偏差的活动为关键活动，需要根据进度偏差值与总时差和自由时差的关系作进一步分析","AE","A项错，如果活动的进度偏差未超过该活动的自由时差，则此进度偏差不影响后续活动，因此原进度计划可以不作调整。 E项错，如果出现进度偏差的活动位于关键线路上，即该活动为关键活动，则无论其偏差有多大，都将对后续活动和工期产生影响，必须采取相应的调整措施；如果出现偏差的活动是非关键活动，则需要根据进度偏差值与总时差和自由时差的关系作进一步分析。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（水利）","建筑工程",0]