[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905313":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},905313,585,2,"多选题","关于混凝土浇筑过程中应注意的事项，下列说法正确的有（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","一般要求清孔换浆以后3h内开始浇筑混凝土",false,{"key":16,"text":17,"correct":18},"B","在槽孔混凝土的浇筑过程中，必须保持均衡、连续、有节奏地施工",true,{"key":20,"text":21,"correct":18},"C","槽孔浇筑应严格遵循先深后浅的顺序",{"key":23,"text":24,"correct":18},"D","保持导管埋入混凝土的深度介于1～6m",{"key":26,"text":27,"correct":18},"E","全槽混凝土面均衡上升，上升速度不应小于2m\u002Fh","BCDE","A项，一般要求清孔换浆以后4h内开始浇筑混凝土。如果不能按时浇筑，应采取措施防止落淤，否则，在浇筑前要重新清孔换浆。B项，浇筑过程中应注意观测，做好混凝土面上升的记录，防止堵管、埋管、导管漏浆和泥浆掺混等事故的发生。保持均衡、连续、有节奏地施工，直到全槽成墙为止。C项，泥浆下浇筑混凝土常用直升导管法。在槽孔浇筑应严格遵循先深后浅的顺序，即从最深的导管开始，由深到浅，一个一个导管依次开浇，待全槽混凝土面浇平以后，再全槽均衡上升。DE两项，在浇筑过程中，应保证连续供料，一气呵成；保持导管埋入混凝土的深度不小于1m，但不超过6m，以防泥浆掺混和埋管；维持全槽混凝土面均衡上升，上升速度不应小于2m\u002Fh，高差控制在0.5m范围内。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（水利）","建筑工程",0]