[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905288":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},905288,585,2,"多选题","土料压实方法主要要求包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","错距法压实",true,{"key":16,"text":17,"correct":14},"B","碾压方向",{"key":19,"text":20,"correct":14},"C","分段碾压碾迹搭接宽度",{"key":22,"text":23,"correct":14},"D","碾压行车速度",{"key":25,"text":26,"correct":27},"E","碾压次数",false,"ABCD","土料压实方法主要要求包括以下几个方面：①错距法压实，是指沿着长度方向前进压实、后退压实一个压实宽度，压实一定遍数之后，再压实下一个压实宽度，第二个压实宽度应与第一个压实宽度有一定的重叠量。此法碾压与铺土、质检等工序分段作业容易协调，便于组织平行流水作业。碾压遍数较少时也可采用一次压够遍数、再错车的方法。②碾压方向，应沿坝轴方向进行。在特殊部位，如防渗体截水槽内或与岸坡结合处，应用专用设备在划定范围沿接坡方向碾压。③分段碾压碾迹搭接宽度，垂直碾压方向不小于0.3～0.5m，顺碾压方向应为1.0～1.5m。④碾压行车速度，一般取2～3km\u002Fh，不得超过4km\u002Fh。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（水利）","建筑工程",0]