[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905113":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},905113,585,2,"多选题","下列疏浚工程项目中，（ ）需要计量支付。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","按设计图纸轮廓尺寸计算的水下有效自然方",true,{"key":16,"text":17,"correct":18},"B","开工展布与收工集合",false,{"key":20,"text":21,"correct":18},"C","施工自然回於量",{"key":23,"text":24,"correct":14},"D","浚前扫床及障碍物清除",{"key":26,"text":27,"correct":14},"E","排泥区围堰","ADE","本题考查的是水利建筑工程工程量清单。在江河、水库、港湾、湖泊等处的疏浚工程（包括排泥于水中或陆地），按设计图示轮廓尺寸计算的水下有效自然方体积计量。施工过程中疏竣设计断面以外增加的超挖量、施工期自然回淤量、开工展布与收工集合、避险与防干扰措施、排泥管安拆移动以及使用辅助船只等所发生的费用，应摊入有效工程量的工程单价中，辅助工程（如浚前扫床和障碍物清除、排泥区围堰、隔埂、退水口及排水渠等项目）另行计量计价。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（水利）","建筑工程",0]