[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905110":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},905110,585,2,"多选题","施工工厂设施包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","混凝土生产系统",true,{"key":16,"text":17,"correct":14},"B","砂石料加工系统",{"key":19,"text":20,"correct":21},"C","转运站",false,{"key":23,"text":24,"correct":21},"D","对内交通",{"key":26,"text":27,"correct":14},"E","机械修配及综合加工系统","ABE","本题考查的是临时设施。施工工厂设施主要包括混凝土生产系统、混凝土制冷（热）系统、砂石料加工系统、机械修配及综合加工系统、风、水、电、通信及照明等。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（水利）","建筑工程",0]