[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905107":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},905107,585,2,"多选题","下列施工进度计划控制措施中属于组织措施的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","明确现场项目管理组织机构中进度控制人员职责",true,{"key":16,"text":17,"correct":14},"B","建立进度协调会议制度",{"key":19,"text":20,"correct":21},"C","对建设工程进度实施动态控制",false,{"key":23,"text":24,"correct":14},"D","编制年度进度计划",{"key":26,"text":27,"correct":21},"E","加强风险管理","ABD","本题考查的是施工进度计划的保证措施。组织措施包括：（1）建立进度控制目标体系，明确现场项目管理组织机构中进度控制人员及其职责分工；（2）建立进度计划实施中的检查分析制度；（3）建立进度协调会议制度；（4）编制年度进度计划、季度进度计划和月（旬）作业计划，将施工进度计划逐层细化。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（水利）","建筑工程",0]