[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905106":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},905106,585,2,"多选题","根据《水利水电工程施工组织设计规范》（SL 303-2017），水利工程建设项目施工总工期是指（ ）之和。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程筹建期",false,{"key":16,"text":17,"correct":18},"B","工程准备期",true,{"key":20,"text":21,"correct":18},"C","主体工程施工期",{"key":23,"text":24,"correct":18},"D","工程完建期",{"key":26,"text":27,"correct":14},"E","工程试运行期","BCD","本题考查的是施工期的划分与编制原则。工程建设全过程可划分为工程筹建期、工程准备期、主体工程施工期和工程完建期四个施工时段，编制施工总进度时，工程施工总工期应为后三项工期之和。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（水利）","建筑工程",0]