[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905094":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},905094,585,2,"多选题","下列关于堤防填筑与压实说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","地面起伏不平时，为加快施工进度可顺坡铺填",false,{"key":16,"text":17,"correct":18},"B","堤防断面上的地面坡度陡于1：5时，应削至缓于1：5",true,{"key":20,"text":21,"correct":14},"C","分段作业面长度应根据施工机械的配备和作业能力确定，以不影响压实质量为原则，最小长度不宜大于100m",{"key":23,"text":24,"correct":18},"D","土料铺填与压实工序应连续进行，以免土料含水量变化过大影响填筑质量",{"key":26,"text":27,"correct":18},"E","严禁砂（砾）料或其他透水料与黏性土料混杂，上堤土料中的杂质应当清除","BDE","本题考查的是土石方填筑工程。选项A错误，地面起伏不平时，应按水平分层由低处逐层填筑，不得顺坡铺填；选项C错误，分段作业面长度应根据施工机械的配备和作业能力确定，以不影响压实质量为原则，最小长度不宜大于100m。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（水利）","建筑工程",0]