[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-905089":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},905089,585,2,"多选题","下列导流方式中属于分期围堰法的的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","底孔导流",true,{"key":16,"text":17,"correct":14},"B","束窄河床导流",{"key":19,"text":20,"correct":21},"C","隧洞导流",false,{"key":23,"text":24,"correct":21},"D","涵管导流",{"key":26,"text":27,"correct":14},"E","缺口导流","ABE","本题考查的是施工导流方式与泄水建筑物。分期围堰法包括底孔导流、坝体缺口导流、束窄河床和明渠导流。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（水利）","建筑工程",0]