[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904998":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},904998,585,2,"多选题","受淹集镇、城镇的迁建，其迁建方式有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","建议撤销或与邻近集镇.城镇合并",true,{"key":16,"text":17,"correct":14},"B","易地迁建",{"key":19,"text":20,"correct":14},"C","就地迁建",{"key":22,"text":23,"correct":14},"D","工程防护",{"key":25,"text":26,"correct":27},"E","工程围挡",false,"ABCD","本题考查的是集镇、城镇迁建规划设计。受淹集镇、城镇的迁建，其迁建方式包括：易地迁建；建议撤销或与邻近集镇、城镇合并；就地迁建；工程防护。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（水利）","建筑工程",0]