[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904951":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},904951,585,1,"单选题","在完成壁后注浆之后，需要进行二次注浆的情况不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","隧道成形后地面沉降仍有较大的变化趋势",false,{"key":16,"text":17,"correct":14},"B","局部地层较软",{"key":19,"text":20,"correct":14},"C","同步注浆注浆量不足",{"key":22,"text":23,"correct":24},"D","压浆时未对称",true,"为了防止地表沉降，必须将盾尾和衬砌之间的空隙及时注浆充填。注浆后还可改善衬砌受力状态，并增进衬砌的防水效果。壁后注浆分为一次注浆和二次注浆。在同步注浆后出现以下情况需进行二次注浆：①隧道成形后地面沉降仍有较大的变化趋势；②局部地层较软；③同步注浆注浆量不足。二次注浆是通过管片中部的注浆孔进行。壁后注浆常用的材料有水泥浆、泥浆和化学浆液等。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]