[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904945":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},904945,585,1,"单选题","下列哪种计划的关键线路是指自终点节点逆箭线方向朝起点节点观察，自始至终不出现波形线的线路？（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","单代号网络计划",false,{"key":16,"text":17,"correct":14},"B","单代号搭接网络计划",{"key":19,"text":20,"correct":14},"C","双代号网络计划",{"key":22,"text":23,"correct":24},"D","双代号时标网络计划",true,"AB两项，在单代号网络计划或单代号搭接网络计划中，从起点节点开始到终点节点均为关键工作，且所有工作的时间间隔仅为零的线路应为关键线路。C项，在双代号网络计划中，自始至终全部由关键工作组成的线路或线路上总的工作持续时间最长的线路即为关键线路。D项，在双代号时标网络计划中，自终点节点逆箭线方向朝起点节点观察，自始至终不出现波形线的线路为关键线路。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]