[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904936":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},904936,585,1,"单选题","关于施工总进度计划的编制，下列说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","系统分析受洪水威胁后全部项目的施工进度计划",true,{"key":16,"text":17,"correct":18},"B","采用先进、合理的指标和方法安排工期",false,{"key":20,"text":21,"correct":18},"C","单项工程施工进度与施工总进度相互协调",{"key":23,"text":24,"correct":18},"D","在保证工程质量与建设总工期的前提下，应研究提前发电和使投资效益最大化的施工措施","编制施工总进度的原则如下：①执行基本建设程序，遵照国家政策、法令和有关规程规范。②采用先进、合理的指标和方法安排工期。对复杂地质、恶劣气候条件或受洪水制约的工程，宜适当留有余地。③系统分析受洪水威胁的关键项目的施工进度计划，采取有效的技术和安全措施。④单项工程施工进度与施工总进度相互协调，做到资源配置均衡，各项目施工程序前后兼顾、衔接合理，减少施工干扰，均衡施工。⑤在保证工程质量与建设总工期的前提下，应研究提前发电和使投资效益最大化的施工措施。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]