[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904855":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},904855,585,1,"单选题","根据《水利水电工程清单计价规范》（GB 50501 -2007），水利水电工程清单编码中五六位代表（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","水利工程",false,{"key":16,"text":17,"correct":14},"B","专业工程",{"key":19,"text":20,"correct":21},"C","分类工程",true,{"key":23,"text":24,"correct":14},"D","分项工程","本题考查的是水利水电工程项目编码。一、二位为水利工程顺序编码，“50”代表水利工程；三、四位为专业工程顺序编码，其中“01”水利建筑工程，“02”水利安装工程；五、六位为分类工程顺序编码，“500110为建筑工程中的模板工程”；七-九位为分项工程顺序编码，“500110001为建筑工程中的普通模板”。十至十二位代表清单项目名称顺序流水号，自“001”起顺序编号。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]