[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904849":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},904849,585,1,"单选题","按招标设计文件要求的有效成品料体积计量，开采、运输、加工、堆存过程中的操作损耗等所发生的费用均应摊入有效工程量工程单价中的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","天然砂料",false,{"key":16,"text":17,"correct":14},"B","块（堆）石料",{"key":19,"text":20,"correct":21},"C","黏性土料",true,{"key":23,"text":24,"correct":14},"D","混凝土半成品料","原料开采及加工工程清单项目包括黏性土料、天然砂料、天然卵石料、人工砂料、人工碎石料、块（堆）石料、条（料）石料、混凝土半成品料、其他原料开采及加工工程。黏性土料按招标设计文件要求的有效成品料体积计量。料场查勘及试验费用，清除植被层与弃料处理费用，开采、运输、加工、堆存过程中的操作损耗等所发生的费用，应摊入有效工程量的工程单价中。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]