[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904842":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},904842,585,1,"单选题","下列有关石方明挖工程的说法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","平面高程一般应不大于0.2m",false,{"key":16,"text":17,"correct":14},"B","边坡开挖高度8m时，一般应不大于0.2m",{"key":19,"text":20,"correct":21},"C","边坡开挖高度8～15m时，一般应不大于0.5m",true,{"key":23,"text":24,"correct":14},"D","边坡开挖高度16～30m时，一般应不大于0.5m","石方明挖工程的要求包括：①平面高程一般应不大于0.2m；②边坡开挖高度8m时，一般应不大于0.2m；③边坡开挖高度8～15m时，一般应不大于0.3m。边坡开挖高度16～30m时，一般应不大于0.5m。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]