[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904841":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},904841,585,1,"单选题","在计算大面积土石方开挖工程量时，适用于地形起伏变化较大的地区，计算较为简便的方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","横截面计算法",true,{"key":16,"text":17,"correct":18},"B","方格网计算法",false,{"key":20,"text":21,"correct":18},"C","地槽工程量",{"key":23,"text":24,"correct":18},"D","地下工程石方工程量","大面积土石方开挖工程量的计算方法主要有横截面计算法、方格网计算法。横截面计算法适于地形起伏变化较大地区采用，计算较简便。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]