[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904838":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},904838,585,1,"单选题","下列关于施工临时工程量的说法不正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工支洞工程量应按永久水工建筑物工程量计算要求进行计算，阶段系数按施工临时工程计取",false,{"key":16,"text":17,"correct":14},"B","施工临时道路的工程量可根据相应设计阶段施工总平面布置图或设计提出的运输线路分等级计算公路长度或具体工程量",{"key":19,"text":20,"correct":14},"C","大型施工设施及施工机械布置所需土建工程量，按永久建筑物的要求计算工程量，阶段系数按施工临时工程计取",{"key":22,"text":23,"correct":24},"D","临时生产用房工程量按现行规定计算，临时生活福利房屋建筑工程量结合工程情况以建筑面积或分项工程量计算",true,"临时生产用房工程量在不同设计阶段结合工程情况以建筑面积或分项工程工程量计算，临时生活福利房屋建筑工程量，按现行规定计算。D选项错。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]