[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904834":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},904834,585,1,"单选题","根据水利工程各专业配合的先后顺序，由水工到施工到机电金结的顺序计算方式是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","按专业顺序计算",true,{"key":16,"text":17,"correct":18},"B","按工程量计算规则的顺序计算",false,{"key":20,"text":21,"correct":18},"C","按现行概预算定额的章节顺序计算",{"key":23,"text":24,"correct":18},"D","按施工顺序计算","能独立发挥作用或独立具有施工条件的建筑物，其工程量计算顺序一般有以下几种：按专业顺序计算；按工程量计算规则的顺序计算；按现行概预算定额的章节顺序计算；按施工顺序计算。按专业顺序计算，即根据水利工程各专业配合的先后顺序，由水工到施工到机电金结的顺序计算。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]