[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904826":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},904826,585,1,"单选题","网络计划优化时，选择应缩短持续时间的关键工作应考虑的因素不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","缩短持续时间对质量和安全影响不大的工作",false,{"key":16,"text":17,"correct":14},"B","充足备用资源的工作",{"key":19,"text":20,"correct":14},"C","缩短持续时间所需增加的费用最少的工作",{"key":22,"text":23,"correct":24},"D","缩短持续时间所需增加的费用最多的工作",true,"网络计划优化时，选择应缩短持续时间的关键工作宜考虑下列因素：①缩短持续时间对质量和安全影响不大的工作。②有充足备用资源的工作。③缩短持续时间所需增加的费用最少的工作。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]