[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904818":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},904818,585,1,"单选题","在区域规划中，利水电工程一般多采用（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","混合式布置",true,{"key":16,"text":17,"correct":18},"B","集中布置",false,{"key":20,"text":21,"correct":18},"C","分散布置",{"key":23,"text":24,"correct":18},"D","区域布置","施工总布置按功能可分为八大主要区域，各施工区域在布置上并非截然分开的，它们的生产工艺和布置是相互联系的，应构成一个统一的、调度灵活的、运行方便的整体。在区域规划时，按主体工程施T区与其他各区域互相关联或相互独立的程度，分为集中布置、分散布置、混合布置三种方式，水利水电工程一般多采用混合式布置。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]