[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904795":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},904795,585,1,"单选题","盾构试掘进的长度一般为始发后（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","80m",false,{"key":16,"text":17,"correct":14},"B","90m",{"key":19,"text":20,"correct":21},"C","100m",true,{"key":23,"text":24,"correct":14},"D","110m","盾构试掘进的长度一般为始发后100m，其目的是通过这100m的掘进，总结出适应本工程地质条件的盾构掘进参数，为盾构正常掘进积累经验。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]