[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904760":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},904760,585,1,"单选题","关于反滤料的铺填，下列说法正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","当反滤层宽度大于5m时，可采用推土机摊铺平整",false,{"key":16,"text":17,"correct":14},"B","当铺料宽度小于2m时，可选用10t以下后卸式汽车运料",{"key":19,"text":20,"correct":14},"C","当反滤层宽度大于2m时，可沿反滤层以后退法卸料",{"key":22,"text":23,"correct":24},"D","填土与反滤料的“犬牙交错”带宽度一般不得大于填土层厚的1.5倍",true,"反滤料填筑工序包括：①卸料。采用自卸汽车卸料，车型的大小应与铺料宽度相适应，卸料方式应尽量减少粗细料分离。当铺料宽度小于2m时，宜选用侧卸车或5t以下后卸式汽车运料。当反滤层宽度大于3m时，可沿反滤层以后退法卸料。反滤料在备料场加水保持潮湿，也是减少铺料分离的有效措施。②铺料。一般较多采用小型反铲（斗容1m3）铺料，也有使用装载机配合人工铺料的，当反滤层宽度大于3m时，可采用推土机摊铺平整。③界面处理。反滤层填筑必须保证其设计宽度，填土与反滤料的“犬牙交错”带宽度一般不得大于填土层厚的1.5倍。④压实。当防渗体土料与反滤料、反滤料与过渡料或坝壳堆石料填筑齐平时，必须用平碾骑缝碾压，跨过界面至少0.5m。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]