[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904751":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},904751,585,1,"单选题","TBM到达掘进的最后（ ）要根据围岩的地质情况确定合理的掘进参数并做出书面交底。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","15m",false,{"key":16,"text":17,"correct":18},"B","20m",true,{"key":20,"text":21,"correct":14},"C","25m",{"key":23,"text":24,"correct":14},"D","30m","掘进机到达前应检查掘进方向以保证贯通误差在规定的范围内。到达掘进的最后20m要根据围岩的地质情况确定合理的掘进参数并做出书面交底，总的要求是：低速度、小推力和及时的支护或回填灌浆，并做好掘进姿态的预处理工作。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]