[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904738":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},904738,585,1,"单选题","在完成壁后注浆之后，需要进行二次注浆的情况不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","隧道成形后地面沉降仍有较大的变化趋势",false,{"key":16,"text":17,"correct":14},"B","局部地层较软",{"key":19,"text":20,"correct":14},"C","同步注浆注浆量不足",{"key":22,"text":23,"correct":24},"D","压浆时未对称",true,"壁后注浆分为一次注浆和二次注浆。 在同步注浆后出现以下情况需进行二次注浆： ①隧道成形后地面沉降仍有较大的变化趋势； ②局部地层较软； ③同步注浆注浆量不足。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]