[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904733":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},904733,585,1,"单选题","20世纪60年代以后，土砂松坡接触平起法已成为趋于规范化的施工方法，下列说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","土砂松坡接触平起法一般分为先砂后土法、先土后砂法、土砂交替法几种",false,{"key":16,"text":17,"correct":14},"B","工程较多采用先砂后土法",{"key":19,"text":20,"correct":14},"C","土砂松坡接触平起法允许反滤料与相邻土料“犬牙交错”",{"key":22,"text":23,"correct":24},"D","先砂后土法，当反滤层宽度较小（＜3m）时，铺2层反滤料，填2层土料",true,"D项错，先砂后土法是指先铺反滤料，后铺土料。当反滤层宽度较小（＜3m）时，铺1层反滤料，填2层土料，碾压反滤料并骑缝压实与土料的结合带。先砂后土法由于土料填筑有侧限、施工方便，工程较多采用。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]