[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904730":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},904730,585,1,"单选题","关于人工开挖土方，下列说法错误的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","不具备采用机械开挖的条件时，可采用人工开挖",false,{"key":16,"text":17,"correct":14},"B","渠道宜采用分段施工的平行流水作业组织方式进行开挖",{"key":19,"text":20,"correct":14},"C","开挖冻土时，可采用爆破松土与装载机配合来提高开挖效率",{"key":22,"text":23,"correct":24},"D","处于河床以下的建筑物基础开挖过程中，临近设计高程时，应留出0.1m的保护层暂不开挖",true,"D项错，处于河床或地下水位以下的建筑物基础开挖，应特别注意做好排水工作。施工时，应先开挖排水沟，再分层下挖。临近设计高程时，应留出0.2～0.3m的保护层暂不开挖，待上部结构施工时，再予以挖除。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]