[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904721":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},904721,585,1,"单选题","施工导流方式，大体上可分为两类，即分段围堰法导流和（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","明渠导流",false,{"key":16,"text":17,"correct":18},"B","全段围堰法导流",true,{"key":20,"text":21,"correct":14},"C","涵管导流",{"key":23,"text":24,"correct":14},"D","淹没基坑法导流","施工导流是指在江河上修建水利水电工程时，为了使水工建筑物能在地上进行施工，需要用围堰维护基坑，并将水流引向预定的泄水通道往下游宣泄。施工导流方式，大体上可分为两类，即：①分段围堰法，又称分期围堰法，是指用围堰将水工建筑物分段、分期维护起来进行施工的方法，一般适用于河床宽、流量大、工期较长的工程，尤其适用于通航河流和冰凌严重的河流。②全段围堰法，是指在河床主体工程的上下游各建一道断流围堰，使水流经河床以外的临时或永久泄水道下泄。ACD三项属于按导流泄水道划分的全段围堰法导流方式。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]