[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904671":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},904671,585,1,"单选题","固定式启闭机安装时，基础螺栓及支撑垫板埋设完毕后应进行的下一步骤是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","安装门架",false,{"key":16,"text":17,"correct":18},"B","安装机架",true,{"key":20,"text":21,"correct":14},"C","安装轨道",{"key":23,"text":24,"correct":14},"D","安装保护元件","固定式启闭机的一般安装程序是： ①埋设基础螺栓及支撑垫板； ②安装机架； ③浇筑基础二期混凝土； ④在机架上安装提升机构； ⑤安装电气设备和保护元件； ⑥连接闸门做启闭机操作试验，使各项技术参数和继电保护值达到设计要求。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]