[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904669":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},904669,585,1,"单选题","下列关于平板闸门安装的说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","门叶尺寸较小在工厂整体预制",true,{"key":16,"text":17,"correct":18},"B","门叶尺寸较大在工厂整体预制",false,{"key":20,"text":21,"correct":18},"C","门槽安装应一次到顶",{"key":23,"text":24,"correct":18},"D","土建和安装单位不应共用脚手架","门叶尺寸较小，则在工厂制成整体运至现场，经复测检查合格，装上止水橡皮等附件后，直接吊入门槽。门叶尺寸较大，由工厂分节制造，运到工地后，再现场组装，然后吊入门槽。A项正确，B项错。 大多数门槽往往不能一次安装到顶，而要随着建筑物升高而不断升高。C项错。 土建单位和安装单位应共同协商使用一套脚手架，既节约搭、拆的直线工期，又节约搭拆费用。D项错。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]