[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904580":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},904580,585,1,"单选题","在混凝土重力坝内，下列哪种情况下不须设置廊道（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","进行帷幕灌浆",false,{"key":16,"text":17,"correct":14},"B","操作闸门或铺设风、水、电线路",{"key":19,"text":20,"correct":21},"C","坝体排水",true,{"key":23,"text":24,"correct":14},"D","坝内交通运输以及检查维修","在混凝土重力坝内，为了下列需要常须设置各种廊道：进行帷幕灌浆；集中排除坝体和坝基渗水；安装观测设备以监视坝体的运行情况；操作闸门或铺设风、水、电线路；施工中坝体冷却及纵（横）缝灌浆；坝内交通运输以及检查维修等。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]