[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904570":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},904570,585,1,"单选题","水库工程中最大高度超过（ ）的大坝建筑物，其级别应为Ⅰ级。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","100m",false,{"key":16,"text":17,"correct":18},"B","200m",true,{"key":20,"text":21,"correct":14},"C","300m",{"key":23,"text":24,"correct":14},"D","400m","水库工程中最大高度超过200m的大坝建筑物，其级别应为Ⅰ级，其设计标准应专门研究论证，并报上级主管部门审查批准。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]