[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904447":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},904447,585,1,"单选题","用相对密度Dr＝0.25，天然孔隙比e＝0.85的某处原状土开挖后运到另一处作回填料，已知土体的最大孔隙比为1.0，则填筑1m3的土需要挖方体积数（ ）m3。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1.07",false,{"key":16,"text":17,"correct":14},"B","1.21",{"key":19,"text":20,"correct":21},"C","1.32",true,{"key":23,"text":24,"correct":14},"D","1.52","根据相对密度的定义有： Dr＝（emax－e）\u002F（emax－emin）又emax＝1.0，e＝0.85，代入解得最小孔隙比为：emin＝0.4。 土体在回填的过程中颗粒体积Vs保持不变，压实后土体达到最小孔隙比。故可得到： Vs＝V\u002F（1＋e）＝V0\u002F（1＋emin）又填筑体积V0＝1m3，代入可得需挖方体积数为： V＝V0（1＋e）\u002F（1＋emin）＝1×（1＋0.85）\u002F（1＋0.4）＝1.32m3。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]