[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904394":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},904394,585,1,"单选题","某土质基坑开挖工程，依照设计图纸尺寸为5m×3m×4m，开挖费用为600元，为了保证施工安全，放坡方量为15m3，超挖量费用为300元，不考虑其他相关费用，则该土方单价为（ ）元\u002Fm3。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":18},"B","15",true,{"key":20,"text":21,"correct":14},"C","12",{"key":23,"text":24,"correct":14},"D","60","本题考查的是水利建筑工程工程量清单。土方开挖工程工程量清单项目的工程量计算规则。按招标设计图示轮廓尺寸范围以内的有效自然方体积计量。施工过程中增加的超挖量和施工附加量所发生的费用，应摊入有效工程量的工程单价中。（600+300）÷（5×3×4）=15（元\u002Fm3）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]