[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904387":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},904387,585,1,"单选题","某施工场地为单向斜面，自然坡度为1%，设计坡度为0.3%，场地整平宽度为100m，则其填挖方总高为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1m",false,{"key":16,"text":17,"correct":18},"B","0.7m",true,{"key":20,"text":21,"correct":14},"C","0.4m",{"key":23,"text":24,"correct":14},"D","0.3m","本题考查的是土石方平衡及渣场规划。挖填总高度=100×1%-100×0.3%=0.7（m）。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]