[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904386":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},904386,585,1,"单选题","某工程网络计划中，工作M自由时差为2天，总时差为5天，实施过程中在进度检查时发现该工作持续时间延长了4天，则工作M实际进度（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不影响总进度，但将该工作的紧后工作的最早开始时间后延了2天",true,{"key":16,"text":17,"correct":18},"B","既不影响总进度，也不影响其紧后工作的正常进行",false,{"key":20,"text":21,"correct":18},"C","将使总工期延长4天，但不影响后续工作正常进行",{"key":23,"text":24,"correct":18},"D","其后续工作的开始时间推后4天，并使总工期延长1天","本题考查的是进度计划实施中的调整方法。M工作为非关键工作，延长4天未超过其总时差，所以不影响总工期，延长时间4天大于其自由时差2天，所以影响该工作的紧后工作的最早开始时间拖后2天。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]