[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904385":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},904385,585,1,"单选题","某工程双代号时标网络计划，在第5天末进行检查得到的实际进度前锋线如下图所示，说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","G工作进度落后1天",false,{"key":16,"text":17,"correct":18},"B","总工期缩短1天",true,{"key":20,"text":21,"correct":14},"C","H工作不影响总工期",{"key":23,"text":24,"correct":14},"D","E工作提前1天完成","本题考查的是进度计划实施中的调整方法。选项B错误，因为G工作是关键工作，G工作延误1天导致总工期延长1天。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]