[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904384":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},904384,585,1,"单选题","下列不属于编制控制性施工进度计划的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分析选定关键性工程项目",false,{"key":16,"text":17,"correct":14},"B","初拟控制性施工进度计划表",{"key":19,"text":20,"correct":21},"C","施工进度比较",true,{"key":23,"text":24,"correct":14},"D","编制控制性施工进度表","本题考查的是进度计划的制订。控制性施工进度的编制包括（1）分析选定关键性工程项目；（2）初拟控制性施工进度表；（3）编制控制性进度表。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]