[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904380":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},904380,585,1,"单选题","某施工单位为满足大坝提前蓄水安排了坝内埋管安装如下图所示，下列施工顺序正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1→2→3→4→5→6",false,{"key":16,"text":17,"correct":14},"B","2→1→3→4→6→5",{"key":19,"text":20,"correct":14},"C","1→2→5→6→3→4",{"key":22,"text":23,"correct":24},"D","2→1→5→6→4→3",true,"本题考查的是压力钢管。为满足大坝提前蓄水要求的钢管安装示意图如下图所示。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]