[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904376":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},904376,585,1,"单选题","固结灌浆通常采用钻孔压水试验和测量岩石弹性模量进行检查，压水试验检查孔数量不宜少于灌浆孔总数（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3%",false,{"key":16,"text":17,"correct":18},"B","5%",true,{"key":20,"text":21,"correct":14},"C","7%",{"key":23,"text":24,"correct":14},"D","10%","本题考查的是灌浆工程。固结灌浆通常采用钻孔压水试验和测量岩石弹性模量进行检查，压水试验检查孔数量不宜少于灌浆孔总数5%。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]