[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904198":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},904198,585,1,"单选题","具有独立的设计文件，竣工后可以独立发挥生产能力或效益的工程，指的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分部分项工程",false,{"key":16,"text":17,"correct":14},"B","单位工程",{"key":19,"text":20,"correct":21},"C","单项工程",true,{"key":23,"text":24,"correct":14},"D","建设项目","本题考查的是工程项目划分。单项工程在水利工程项目划分中称为“一级项目”，是具有独立的设计文件，竣工后可以独立发挥生产能力或效益的工程。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]