[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904172":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},904172,585,1,"单选题","对于综合利用的水利工程，如按各综合利用项目的分等指标确定的等别不同时，其工程等别应按其中的（ ）确定。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最低等别",false,{"key":16,"text":17,"correct":18},"B","最高等别",true,{"key":20,"text":21,"correct":14},"C","中间等别",{"key":23,"text":24,"correct":14},"D","中高等别","本题考查的是水利工程等别划分。对于综合利用的水利工程，如按各综合利用项目的分等指标确定的等别不同时，其工程等别应按其中的最高等别确定。",{"id":6,"name":27,"category":28,"favorite":29},"建设工程技术与计量（水利）","建筑工程",0]