[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904161":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},904161,584,2,"多选题","公路工程造价的监督内容及程序分为（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","项目建设前期",true,{"key":16,"text":17,"correct":14},"B","项目实施阶段",{"key":19,"text":20,"correct":14},"C","项目决算阶段",{"key":22,"text":23,"correct":24},"D","项目结束阶段",false,{"key":26,"text":27,"correct":24},"E","项目监督阶段","ABC","公路工程造价的监督内容及程序分为三个阶段：①项目建设前期。项目建设前期造价监督是指从项目立项至招投标结束期问有关工程造价的监督和管理。②项目实施阶段。项目实施阶段造价监督是指项目开工后至交工验收前有关工程造价的监督和管理。③项目决算阶段。工程决算是建设项目竣工验收工作的重要组成部分。未编制工程决算的建设项目，不得组织竣工验收。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]