[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904152":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},904152,584,2,"多选题","公路建设工程的招标文件工程量清单须按交通运输部规定的格式填写，如果发现（ ）情况的，将由造价管理部门报交通运输主管部门追究编制单位的责任。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","工程数量存在重大偏差的",true,{"key":16,"text":17,"correct":14},"B","招标控制价的制定与法律.法规存在冲突的",{"key":19,"text":20,"correct":14},"C","招标控制价与监督检查的结果相差较大且无合理解释的",{"key":22,"text":23,"correct":24},"D","招标控制价远远高于投标报价",false,{"key":26,"text":27,"correct":14},"E","其他失误造成招标控制价重大偏差的","ABCE","本题考查的是各阶段公路工程造价的监督内容及程序。若发现以下情况之一的，将由造价管理部门报交通运输主管部门追究编制单位的责任：（1）招标控制价的制定与法律、法规存在冲突的；（2）工程数量存在重大偏差的；（3）招标控制价与监督检查的结果相差较大且无合理解释的；（4）其他失误造成招标控制价重大偏差的。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]