[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-904145":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},904145,584,2,"多选题","定额单价分析法计算直接工程费的步骤包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","选用与工作内容相适应的工、料、机消耗定额",true,{"key":16,"text":17,"correct":14},"B","分析工、料、机单价",{"key":19,"text":20,"correct":21},"C","根据施工组织设计中确定的数量进行计算费用",false,{"key":23,"text":24,"correct":21},"D","根据企业颁发的类似项目劳务分包单价计算",{"key":26,"text":27,"correct":14},"E","分析确定工程量清单所列细目所包含的工作内容和相关要求","ABE","定额单价分析法计算直接工程费的步骤如下：①分析确定工程量清单所列细目所包含的工作内容和相关要求；②分析工、料、机单价；③选用与工作内容相适应的工、料、机消耗定额；④计算直接工程费。CD两项均属于项目成本分析法的计算要求。",{"id":6,"name":31,"category":32,"favorite":33},"建设工程技术与计量（交通）","建筑工程",0]